Delta Enerji has started producing electricity on 22 April 2009
01.04.2012

 

Delta Enerji has commenced electricity production on April 22 nd 2009 via its 62 MW Natural Gas Fired Combined Cycle Power Plant (CCPP) in Luleburgaz / Kirklareli.
Delta Enerji Üretim ve Ticaret A.Ş. has received an Electricity Production Licence from EMRA which allows for 49 years of production starting on March 13 th , 2008.
Delta Energy has completed the first phase of the plant construction (50 MW) and has received all the necessary approvals from TEIAS (State High Voltage Grid Operator) starting to feed electricy to the Turkish 154 KV Grid. The Engineering Design, Procurement, construction and equipment installation of the Delta Combined Cycle Power Plant Project was accomplished by PALMET Engineering  (PALMET Mühendislik Taahhüt Servis Endüstri ve Ticaret A.Ş.)